Get Listed
Sign In
ThermTech were asked to design, manufacture, and supply & install two replacement economisers for the hospitals waste heat steel boiler.
The economisers will together exchange 449 kw of heat ant thereby heat 4,600 KGH of DFW from 85°C to 168°C.
Based on performance of other similar economisers that we have installed over the years the savings will be of the order of £100,000 per annum.
In addition the reduction in CO2 emissions made by the economiser will be 835 tons per annum.
Case Study 5
Capital Cost £107K
Payback 12 Months
For more information on Case Study: Economiser – Liverpool Hospital talk to ThermTech Ltd
More related to Case Study: Economiser – Liverpool Hospital
Welcome back to FindTheNeedle.
Not registered? Get listed — most visitors don't have an account yet.
List your company on FindTheNeedle.