ALE has successfully completed the weighing, transportation and load-out of a single module, combined of three components, which will form part of a structure set to become the world’s biggest turret when it arrives in South Korea. ALE used 600t jacks and load cells to weigh modules M1, M2 and the grillage, which had a combined weight of 3.395t. These components were then transported and loaded-out using 176 axle lines of SPMT. The whole operation took three days.