Find The Needle Add My Company
Update - Precast Panels, Slats and Beams for MBT Plant at Northacre RRC
Working with RSG Structures Ltd and Interserve Ltd, ACP Concrete manufactured and supplied precast wall panels, slats and beams for the new Mechanical Biological Treatment Plant within the Northacre Resource Recovery Centre in Wiltshire. During construction ACP supplied & RSG installed: 84 nos wall panels in 5 days on site, 237 nos slats in just 11 days and 78 nos precast beams in 4 days. A total of nearly 1200t of concrete! The plant is is a major investment by Hill Waste Solutions, a family owned business with over 100 years of knowledge & experience, who offer a range of specialist waste management and recycling services for both public and private sectors. The new plant, due to be fully completed in summer 2013, will be used to turn 60,000 tonnes of household waste from landfill into Refuse Derived Fuel to create energy, saving Wiltshire tax payers £4.8m per year in land fill tax.

For more information on Update - Precast Panels, Slats and Beams for MBT Plant at Northacre RRC talk to ACP Concrete Ltd

Enquire Now

  Please wait...

Location for : Listing Title